Before SCDES performs a site evaluation, R.61-56.104 requires the applicant to prepare the lot — seven specific things. Miss one and the visit can be wasted. Almost nobody tells homeowners this in advance, so here it is as a checklist.
• A boundary plat, deed, or other legal document specifying lot size
• A legal description with lot boundary lengths — required for lots two acres or smaller, and on request for larger lots
• Written permission for SCDES representatives to access the property, on the Department’s form
• Easements for ingress and egress, if the system will use a remote subsurface wastewater infiltration area
Requirements drawn from S.C. Code Regs. R.61-56.104. SCDES may request additional information, and your regional office is the authority on your specific application. Except for systems designed by a Registered Professional Engineer, installers must arrange the final inspection with the Department in advance.
Step 1: Prepare the Lot
This is the part that surprises people. Before a site evaluation is performed, the applicant is required to do the work above — clear and mark boundaries, post an identification marker, stake the proposed building corners, mark the stub-out and tank location, mark the drain field area, locate the well, and identify any other structures planned.
None of it is difficult. All of it takes time you’d rather not discover you need on the morning of the evaluation.
Get Free Quotes From Local Septic Pros
Three fields, about fifteen seconds. No cost and no obligation.
We pass your request to licensed local companies so they can quote you directly. Your details are never published or sold on.
Step 2: Submit the Application
The applicant must furnish complete and accurate information for determining feasibility, in the format SCDES specifies. Alongside that:
Written permission for access. The property owner or their legal representative must give written permission, on a Department form, for SCDES representatives to enter the property.
Proof of lot size. A boundary plat, deed, or other legal document specifying lot size.
A legal description with boundary lengths — required for lots two acres or smaller, and on request for anything larger.
Easements, if applicable. Where the dwelling will be served by a remote subsurface wastewater infiltration area — a drain field located off the parcel — you must provide easements allowing ingress and egress for construction and operation.
Step 3: The Site Evaluation
SCDES assesses soil and site conditions to determine what your property can support. Setback distances are verified from wells, property lines, surface water bodies and structures. System sizing is calculated from bedroom count, percolation rates and expected daily flow.
Where the Department deems it necessary, required site alterations — swales, fill, shaping — must be completed before the installation is permitted. That’s worth knowing early, because it can add a step and a cost you didn’t budget for.
Step 4: Permit to Construct
SCDES reviews the proposed design against R.61-56 standards and issues the permit.
Reported review times run 4 to 8 weeks, with the Lowcountry and Grand Strand running longer during peak construction season. Permit volume in South Carolina has grown sharply with coastal residential development, which has put pressure on processing in the fastest-growing regions.
Timeline figures come from industry sources rather than SCDES publications. Your regional office can give you the current wait.
Step 5: Installation
The system is built to the permitted design. Changes to tank location, drain field layout or system type require a permit modification before proceeding — not after.
R.61-56.203 sets construction standards that are worth knowing even if someone else is doing the work:
The system area must be protected from surface water and roof or downspout drainage using drainage swales and small amounts of fill to achieve positive surface drainage. Gross dirt, mud and debris must be removed from the tank before backfilling, and all backfill around the tank must be tamped. Multi-part slab lids must have joints caulked or covered. Two-piece tongue-and-groove tanks must be sealed with bituminous mastic or equivalent watertight caulking placed in the groove.
Step 6: Final Inspection
Except for systems designed by a Registered Professional Engineer, installers must arrange the final inspection with SCDES in advance.
Do not backfill before the inspection. Covering a system before it’s inspected can mean excavating and re-exposing every component at your expense.
Step 7: Approval to Operate
Once the inspection passes, SCDES issues final approval and the system is authorized for use.
What About Repairs?
Under R.61-56.104, the Department may also require a permit to construct and approval to operate for the repair, relocation, or replacement of a system or its components when deemed necessary — irrespective of whether there’s any change in use.
So a repair isn’t automatically permit-free. If you’re doing anything beyond routine maintenance, ask before you start.
Who Can Install It
South Carolina reportedly uses a three-tier installer licensing system under R.61-56, with most standard residential installations requiring a Tier 1 installer — and homeowner self-installation is not permitted.
That’s a meaningful difference from states like Pennsylvania and Michigan, which do allow homeowners to install their own systems.
The tier structure and the self-installation restriction come from industry sources. Confirm with your SCDES regional office before making plans around either.
Local rules vary a great deal by county — mandatory connection distances, lake buffers, pre-sale inspections and repair grants. See our South Carolina septic permits by county guide.
Need Help With New Installation?
Tell us what’s going on and we’ll connect you with a licensed South Carolina provider. Free, and no obligation.
Independent — not affiliated with the South Carolina Department of Environmental Services or any county health department, and not a septic contractor.
Frequently Asked Questions
What do I need to do before a septic site evaluation in SC?
Under R.61-56.104 you must clear and mark boundary lines and corners, post an identification marker in the front center of the lot, stake the proposed building corners, mark the stub-out and tank location, mark the drain field area, locate the well, and identify any additional structures planned.
What documents does the application require?
Written permission for SCDES access on a Department form, a boundary plat or deed specifying lot size, a legal description with boundary lengths for lots two acres or smaller, and easements if a remote infiltration area will be used.
How long does a South Carolina septic permit take?
Reported review times run 4 to 8 weeks, longer in the Lowcountry and Grand Strand during peak construction season. Your SCDES regional office can give you the current wait.
Can I backfill before the final inspection?
No. Covering the system before inspection can result in a requirement to excavate and re-expose all components at your expense. Except for engineer-designed systems, installers must arrange the inspection with SCDES in advance.
Can I install my own septic system in South Carolina?
Reportedly not. South Carolina uses a three-tier installer licensing system under R.61-56, and installations must be performed by a licensed installer. Confirm with your SCDES regional office.